Avoca Zone Substation – 11kV switch room – Ausgrid

Client: Energy Australia

VAlue: $2,100,000

Architect: Architects Johannsen & Associates

Project Details

This industrial project consisted of the construction of the new 11kV switch room was adjacent to the existing Avoca Zone power substation. Works included a new cable marshalling area below ground level with the switch and control rooms above at ground level. Conduits were installed between the existing “live” electricity substation and the new building with conduit feeder line left 3m outside the building footprint for future connection.

Due to the location of the project adjacent to Avoca Creek, not only were there strict environmental controls but the water table meant that we were constantly dealing with an ingress of ground water. Driven piles were specified, however the unsuitable sub grade meant that we needed to install a concrete piling platform so that the piling rig could operate.

The Avoca Zone power switch room project was completed under a Lump Sum AS2125 contract.

DURATION

28 weeks

Recent Projects

A render of North Constructions completed project at Mackillop College

Mackillop Catholic College

Under Construction – Two Stage Project consisting of Demolition of existing Buildings and Construction of 2 x…

Read More
A render of the completed North Construction build of Ingenia Blueys Beach Clubhouse

Ingenia Blueys Beach Clubhouse

Under Construction

Read More
A render of Bindaree Rendering Plant

Bindaree Rendering Plant

Under Construction – North will coordinate and manage all works associated with the project, including site preparation,…

Read More
Scroll to Top